Al-Zour North power project to add 2,942 MW, 120 million gallons of water by 2029

  • Construction is advancing on phases 2 and 3 of Kuwait’s strategic power and desalination project, with gas turbines targeted for completion in the second quarter of 2029 and full commercial operation expected by year-end.

Construction work is progressing on Kuwait’s Al-Zour North Power Generation and Water Desalination Plant, phases 2 and 3, a major strategic project expected to add 2,942 megawatts of electricity generation capacity and 120 million imperial gallons of water per day to the country’s national supply.

The project, which is being implemented by Saudi Arabia’s ACWA Power in cooperation with local companies, is moving from preparatory activities into major construction works, with engineering and technical teams working on several key components of the facility.

According to the project schedule, the gas turbine units are expected to be completed in the second quarter of 2029, followed by the steam turbine units and the start of full commercial operations in the fourth quarter of the same year. The contractual implementation period is 42 months.

During a field visit to the site, Ayman Al-Hajji, Director of the Private Sector Projects Department at the Ministry of Electricity, Water and Renewable Energy, reviewed progress on construction activities and preparations for the station’s infrastructure.

Al-Hajji said the Gulf Alliance Company was completing the financial closure procedures alongside ongoing construction work. The process is in its final stages and involves securing the necessary approvals from local and international banks participating in the project’s financing.

He explained that finalizing the financial arrangements would allow the power and water purchase agreement to become fully effective and enable the project to proceed with its contractual obligations and financing requirements.

On-site activities have expanded beyond initial preparations to include construction of the seawater intake facility, which is essential for the station’s cooling operations. Work is also under way to expand the main 400-kilovolt substation, which will transmit electricity generated by the plant to the national grid.

Construction has also started on the foundations of key operational buildings, including the electrical control building and instrumentation building, which will house systems required for monitoring, controlling and operating the facility.

The project comprises two main components. The first includes four gas turbine units, each with a generation capacity of 511 megawatts, providing a combined 2,044 megawatts. The second consists of two steam turbine units, each producing 450 megawatts, adding another 900 megawatts. Together, the units will provide a total generation capacity of 2,942 megawatts.

The station will use H-Class gas turbines, among the largest generation units to be installed at power plants in Kuwait, giving the project considerable technical significance.

Al-Hajji said the additional capacity would strengthen Kuwait’s electricity generation reserves, improve grid stability and help the country meet rising demand, particularly during the summer months when consumption reaches its peak.

He stressed that the importance of the project extends beyond increasing electricity production, as it will also strengthen the country’s water and power infrastructure and support growing urban and economic requirements.

Al-Hajji also underlined the importance of maintaining the implementation schedule amid regional developments and potential supply-chain challenges. He said continued coordination between the relevant authorities and the implementing company would be essential to address obstacles and ensure progress according to the approved timetable.

The power and water purchase agreement for phases 2 and 3 was signed with Gulf Alliance Company on February 3, establishing the contractual framework for the project’s implementation.




Follow The Times Kuwait on X, Instagram, Facebook and Whatsapp Channel for the latest news updates


 






Read Today's News TODAY...
on our Telegram Channel
click here to join and receive all the latest updates t.me/thetimeskuwait



Back to top button