Al-Mutla’a city houses will get power supply next March

The Ministry of Electricity and Water expects to start receiving requests from citizens to connect power supply in the city of Mutla’a during March.

The sources told a local Arabic daily, that the transmission networks sector completed last week the operation of all 400 kV ultra-high voltage stations in the region to operate at full capacity of about 4,000 megawatts — 1Z, 2Z, 3Z, and 4Z.

The sources explained that at the beginning of next February it is planned to operate 36 11/132 kilovolt main substations which will start operating successively and according to the set time plan.

The sources pointed out that once the low-voltage stations are operational, the distribution networks sector will be able to deliver the current to the ready-made distribution substations in the region.