Steam unit at Al-Sabia reinstalled, test-operated - official
May 25, 2015, 5:00 pm
Share/Bookmark

The Steam unit No. 20 at Al-Sabia Power Plant that broke down in January, has been reinstalled, with 220 megawatt capacity, a Ministry of Electricity and Water official has said. The unit is being test-operated, the ministry's Assistant Undersecretary for Operating and Maintenance at the Fouad Al- Oun said in a statement on Monday.

He noted that all the plant's gas and steam units will be ready with their full capacity by June. The Ministry has taken the necessary precautions for the hot summer season after completing maintenance operations, Al-Oun said. 